By Erin Baker and Matthew Lackner | –
The United States’ offshore wind industry is tiny, with just seven wind turbines operating off Rhode Island and Virginia. The few attempts to build large-scale wind farms like Europe’s have run into long delays, but that may be about to change.
The Biden administration announced on March 29, 2021, that it would accelerate the federal review process for offshore wind projects and provide more funding. It also set a goal: Develop 30,000 megawatts of offshore wind capacity this decade – enough to power 10 million homes with clean energy. To put that in perspective, the U.S. has just 42 megawatts today.
Several wind farm developers already hold leases in prime locations off the Eastern Seaboard, suggesting plenty of interest. So, will the government’s new goals and promise of additional funding be enough to finally launch a thriving offshore wind industry?
Biden Administration Aims To Have 20 Million Homes Powered By Offshore Wind By 2023 | NBC News NOW
As engineering professors leading the Energy Transition Initiative and Wind Energy Center at the University of Massachusetts Amherst, we have been closely watching the industry’s challenges and progress. The process could move quickly once permitting and approvals are on track, but there are still obstacles.
Why offshore wind plans stalled under Trump
Vineyard Wind, which is likely to become the nation’s first commercial-scale offshore wind farm, had planned to begin construction in 2019 about 15 miles off Martha’s Vineyard. A ruling by the federal Bureau of Ocean Energy Management under the Trump administration stalled it, and also cast a shadow over other wind farm plans.
The agency ruled that the developers needed to address what is called “cumulative impacts” – what the East Coast will look like when there are not one or two, but 20 or 40 large-scale wind farms. That part of the U.S. coast is ideal for wind power because of its wide, shallow shelf and proximity to cities that are looking for renewable electricity to reduce their climate impact.
Many researchers studying offshore wind, including some of our colleagues, urge planners to take this perspective. But, thinking carefully about the far future does not justify a delay in the first utility-scale wind farm.
That first large wind farm should be an opportunity to learn, including about how wind turbines will interact with marine ecosystems. Right now, there is almost no data on the impacts of offshore wind on marine wildlife – birds, bats, whales, fish – especially on wildlife that is native to New England. The knowledge gained will be invaluable in moving forward responsibly.
Is fast-tracking federal approvals enough?
Speeding up federal approvals for offshore wind farms is an important first step, but those aren’t the only hurdles for offshore wind farm developers.
A large number of state environmental and coastal agencies still must approve, and the communities where cables come ashore will also have a say. Many of the Northeast states have their own offshore wind energy goals, so they’re likely to support wind farms, but some wealthy communities and the fishing industry have pushed back on wind power in the past.
The federal approval process, even fast-tracked, is also time-consuming. The government conducts reviews and requires site assessment plans, including geological, environmental and hazard surveys. From planning to construction, the entire process can take five to six years or more.
Is the US ready to build offshore turbines?
Some other big questions revolve around construction.
Under a 1920 law known as the Jones Act, only U.S.-registered vessels operated by U.S. citizens or permanent residents can move cargo between U.S. ports. In December 2020, Congress made clear that this law applies to wind turbine construction, too.
When companies build offshore wind turbines today, they use special vessels for the installation of the most common offshore turbine designs. The U.S. doesn’t have any of these vessels yet, and the Jones Act makes it difficult to rely on vessels from Europe to do the job. There is promise, though: The first U.S.-made version of this vessel is being built in Texas right now. That’s one – the country will need several to meet the new goal.
A thriving wind power industry will also need ports for storing and deploying the long turbine blades, plus a trained workforce for construction and turbine maintenance.
A few coastal states have a head start on this. Massachusetts started laying the groundwork early and already has a port terminal in New Bedford to support the construction and deployment of future offshore wind projects. New Jersey recently announced a plan for a new offshore wind port that will start construction in 2022.
States are also investing in training. New York state announced a $20 million offshore wind training institute in January 2021 with the goal of training 2,500 workers for the industry and maintenance. The Biden administration envisions 44,000 people employed in offshore wind by 2030 and many more in communities connected to offshore wind power activity.
Will offshore wind pay off?
In Europe, where many governments have reduced regulatory risk, the cost of offshore wind energy has come down rapidly, much faster than experts expected, to around $50 per megawatt-hour. If the Biden administration’s new approach allow U.S. wind farms to achieve costs like this, then offshore wind, with its proximity to large urban centers on the East Coast, will be competitive.
It’s also important to recognize other benefits. Every year of delay for a large-scale wind farm costs the U.S. hundreds of millions of dollars in climate benefits. The Biden administration calculates that its new wind power goal would avoid 78 million metric tons of carbon dioxide, roughly equivalent to taking 17 million cars off the road for a year.
[Get the best of The Conversation, every weekend. Sign up for our weekly newsletter.]
Erin Baker, Professor of Industrial Engineering applied to Energy Policy, University of Massachusetts Amherst and Matthew Lackner, Professor of Mechanical Engineering, University of Massachusetts Amherst
This article is republished from The Conversation under a Creative Commons license. Read the original article.